January 2026 marks another major milestone at Rambler Tempe, now just seven months from opening. With steady construction progress over the fall and key features like windows, lighting, and flooring already in place, we’re starting to see the full shape of the building take form, inside and out.
And have you heard? We’re now offering early move-in as soon as July 24—giving some residents the chance to settle in ahead of the fall semester. Explore our available floor plans to find the space that fits your lifestyle.
Today we’ll be providing updates on:
- Exterior
- Interior and Units
- Amenity Areas
Exterior
Rambler Tempe officially topped out on May 22, 2025, marking a key construction milestone and reaching its peak height. Exterior finishes are progressing steadily across the site, with all windows installed and exterior paneling going up.

Exterior of Rambler Tempe as of December 2025.

Exterior of Rambler Tempe.
Interior and Units
Flooring, cabinetry, and appliances are now installed across much of the building, with cabinetry complete through Floor 15, flooring finished through Floor 12, and appliances installed through Floor 8.
Bathrooms are also nearing final completion, with tilework and lighting fixtures going in units throughout the building.

Kitchen in Rambler Tempe, featuring cabinetry, flooring, appliances and fixtures.

Pull-out trash bin in kitchen drawers at Rambler Tempe.

Bathroom in Rambler Tempe, with tile flooring and lighting fixtures installed.

Living room in Rambler Tempe, with floor-to-ceiling windows and pendant lighting.

Living room in the Sierra floor plan at Rambler Tempe.

Bedroom in Rambler Tempe, featuring installed ceiling fan.
Amenity Areas
From study rooms to wellness areas, Rambler Tempe’s amenities continue to progress. Drywall is now fully in place throughout the lobby, second-floor study mezzanine and private study rooms, giving these areas clearer shape and form.
The rooftop pool deck is taking shape, with surface preparation underway.
Work has also begun in the sauna, offering a first glimpse at the wellness spaces Rambler Tempe will bring to residents this fall.

Sauna at Rambler Tempe, with framing and insulation underway.

Dry wall is in at the two-story fitness center at Rambler Tempe.

The 5th-Floor pool deck taking shape at Rambler Tempe.

Dry wall is in on the study floor at Rambler Tempe.

The lobby at Rambler Tempe begins to take shape, with the fireplace and study mezzanine seen here.
With appliances installed, drywall complete in amenity spaces and exterior finishes continuing to go up, Rambler Tempe is steadily moving toward an on-time completion.
Over the next few weeks, you’ll see continued progress on amenities, lobby details and final appliance installs. And if you’re already counting down the days, here’s some good news: an early move-in option will be available starting July 24, 2026, giving future residents a chance to settle in before the school year begins.
We’ll keep bringing you behind the scenes as Rambler Tempe transitions from an active construction site to a fully livable space, ready to welcome its first residents this August.