Rambler Tempe continues to take shape as construction progresses toward an on-schedule August 2026 opening. With significant updates happening across units, amenities and exterior finishes, February brings another clear step forward in the transformation of the building.
This month’s update covers:
- Exterior
- Interior and Units
- Amenity Areas
Exterior
The front entrance is nearing completion, with brickwork and window installation now finished. As exterior detailing wraps up, Rambler Tempe’s street presence is becoming more defined and polished, offering a first glimpse of the experience residents will have from the moment they walk up.

Front entrance brickwork and window installation completed at Rambler Tempe.
Interior and Units
All flooring in units is now complete, and floors 5–8 are currently being finalized for punch inspections. Lighting is fully operational on multiple residential floors, bringing the spaces to life and allowing final detailing to move forward efficiently. Penthouse units are also seeing backsplash and pendant lighting installation, adding a refined, elevated finish to these top-floor homes.

Penthouse kitchen backsplash and pendant lighting installation in progress.

Bright, modern finishes coming together inside Rambler Tempe units.

Washer and dryer units are now in place through level 13.

Bedroom in Rambler Tempe, featuring installed ceiling fan and rolling blinds.
Amenity Areas
Wellness Spaces
Rambler Tempe’s wellness amenities are taking shape in a big way. Tiles have been placed in the sauna and cold plunge areas, with window views beginning to frame the experience. The red light therapy room has also been framed and is part of the growing recovery suite residents will enjoy.
In the courtyard, tile placement is complete, turf installation is underway and barrel saunas will soon be added, creating an outdoor wellness retreat in the heart of the building.

Sauna at Rambler Tempe with sauna wood now in place.

Entrance to Rambler Tempe’s dedicated wellness space featuring a red light therapy room.

Courtyard tile finished with turf currently being laid.
Pool Decks
The 14th-floor pool deck continues to progress, with hot tub tile installation underway and views becoming more visible as work advances. The 5th-floor pool deck is also taking shape, creating multiple elevated outdoor spaces for residents to relax and gather.
A jumbo screen installation is now in progress, setting the stage for future watch parties and rooftop events.

Hot tub tile coming together.

Rooftop jumbotron taking shape for future events.
Clubhouse & Daydreamer
The 5th-floor clubhouse is quickly transforming, with lighting turned on, upholstery completed and countertops installed. Bathrooms within the clubhouse are also nearing completion, bringing this social hub closer to its final form.
Daydreamer and the on-site bodega are progressing, along with the adjacent patio space creating a built-in coffee and convenience experience for residents.

Clubhouse upholstery and countertops currently underway.

Hardwood flooring completed in Rambler Tempe’s 14th-floor club room.

Completed lighting and tiling in the clubroom as flooring work continues.

Construction progress on the upcoming Daydreamer café space.

Wall cutouts for the Daydreamer bodega at Rambler Tempe.
Study & Fitness Areas
The study rooms and mezzanine are now receiving glass doors and painted accent walls, adding personality and warmth to these focused workspaces. Both the gym and study rooms have been fully painted, and the staircase framing in the fitness center is now in place. Water fountains are also being added throughout the common areas, and the parcel locker room is fully lit and nearing completion.

Glass doors and painted accent walls completed in the private study rooms.

Beautiful 14th-floor views of Tempe from the two-story fitness center.

Common amenity spaces now feature water fountains.
Lobby Updates
The lobby fireplace is now installed, anchoring the space as a central design feature. With drywall complete and finishes going in, the lobby is beginning to reflect the welcoming atmosphere residents will experience daily. Nearby, a dedicated package room will include secure lockers for resident deliveries.

Work continues on the Rambler Tempe lobby fireplace.

Lobby staircase leading to the second-floor study mezzanine with completed railing.

Rambler Tempe secure package room with newly installed lighting.
With unit flooring complete, elevators running, major amenity work underway and exterior finishes nearing completion, Rambler Tempe is entering its final construction stretch. Over the coming weeks you’ll see continued work on wellness amenities, rooftop spaces and detailed interior finishes.
Early move-in remains available beginning July 24, 2026 giving future residents the opportunity to settle in before the fall semester begins.
We’re excited to continue sharing the transformation as Rambler Tempe shifts from a construction site to a fully realized student living community ready to welcome its first residents this August.